Capital Works - Kildare Campus

Kildare Campus Progress Update

Works are progressing smoothly at our new campus on Mt Terrick Rd, and there is much to be excited about as we edge closer to our vision of becoming a multi campus College. Next time you're out and about in the car, be sure to do a drive-by and see the transformation for yourself!

 

Progress to date:

  • External fencing installed
  • Front Entry and Exit gate brickwork footings completed
  • Dam excavation, pump and pump shed enclosure completed
  • Basketball Courts base and asphalt applied
  • Inground services including electrical, sewer, stormwater and water tapping from town along Mt Terrick Rd 
  • Roadways carpark, kerb and channel & street lighting completed
  • Administration and General Learning building concrete slabs poured 
  • Bike Shelter Footing completed and Bike Shelter structure on site
  • Admin building steelwork, roof trusses, wall framing completed
  • Sewer Pumping Station installed
  • Electrical sub-station surveyed and roughed in for slab preparation.

 

Next two weeks:

  • Continue construction of Administration Building
  • Framing of General Learning Building