Kildare Campus Update

The rate of progress currently occuring at Kildare Campus is outstanding! In particular the brickwork which is going up at a rapid rate on our Specialist Building!

 

Stage 2 building works continue to progress as anticipated and we are still on track for completion at the end of April 2024.

Current Progress

  • Specialist Building roofing - 95% complete
  • Specialist Building wall framing - 100% complete
  • Specialist Building rough in services - 90% complete
  • Learning Building roofing - 70% complete
  • Learning Building wall framing - 95% complete
  • Specialist Building solar installation– 95% complete
  • Learning Building solar installation– 10% complete
  • Specialist Building window/door frame installation - 100% complete
  • Slider door tracks to both buildings – 100% complete
  • Specialist Building Facias – 75% complete
  • Bricklayers commenced – 5% complete
  • Plasterers commenced - 5% complete

Upcoming Progress

The Specialist Building is anticipated to be at lock up stage with some joinery to be installed before Christmas which is very exciting!

New Learning Hub

A new Learning Hub was installed at Kildare Campus last week next to our Stage 2 Learning Building and is a welcome addition that will provide more classroom and/or activity space as we grow next year.  Once fitted out, the Learning Hub will also have a deck and garden installed around the perimeter, making for a highly functional and beautiful multipurpose space! 

 

 

 

 