Davies Road Redevelopment

The Road Redevelopment Project for Davies Road between Lapsley Road and Alfred Road is scheduled to commence on Monday 6 May 2019. The Council hope to have works completed before Friday 14 June 2019, weather and contractor availability permitting.

 

The proposed sequence of works is:

 

Week 1 - 2: from Monday 6 May until and including Friday 17 May. 

  • Remove the existing kerb, remove existing median island, install drainage pits, install retaining walls where applicable.

 

Week 3-4: from Monday 20 May until and including Friday 31 May. 

  • Remove existing road surface, install new kerbs and median islands, install new asphalt road surface, backfill behind kerbs, plant new street trees.

Week 5-6: General clean up and reinstatement.

Works are expected to occur during normal working hours between 7:00am and 5:00pm on weekdays. Some Saturday work may occur to complete the project on time.

 

Some crossovers may need to be modified by the Town’s contractor to better match any new road or kerb levels.