The Building Works...

Week 8
In Week 8, we took possession of the new relocatable classrooms. Students from 3/4K and 3/4W were very excited to move in and begin their learning in the fresh new space.
Across from the relocatable classrooms, the new building pads are taking shape. It’s exciting to see how the plans are coming together and how the new spaces will fit within our school.
Week 7
This is an exciting week for our 3/4 classes, as their new relocatable classrooms have arrived. After weeks of waiting, the buildings were installed and in place within just a few hours.
Week 6
Monday 25th August the walk way attaching the builds was removed. Along with all cladding that was on the walls.
The Hands on Learning building has be completly cleared away and the roof of the science room has been removed
The crushing of Building B, Art, Science, and Staffroom areas
Week 5
This week we’ve seen some exciting progress with the building works around the school. All the preparation from the electricians, security teams, plumbers, and builders is now starting to show results.
Work has also begun on the back oval for the new relocatable classrooms, which will be arriving on Monday. Plumbers and electricians have been busy digging trenches to supply services to the new buildings.
On Thursday 21st, the Hands on Learning portable was demolished. Students enjoyed watching the excavator at work—it didn’t take long before the building came down!
The demolition crew has also been busy inside Building B which is the Art, Science, and Staffroom areas. On Thursday, we saw some of the roof removed as part of the process.