The Building Works...

Week 5

This week we’ve seen some exciting progress with the building works around the school. All the preparation from the electricians, security teams, plumbers, and builders is now starting to show results.

 

Work has also begun on the back oval for the new relocatable classrooms, which will be arriving on Monday. Plumbers and electricians have been busy digging trenches to supply services to the new buildings.

Gallery Image
Gallery Image

On Thursday 21st, the Hands on Learning portable was demolished. Students enjoyed watching the excavator at work—it didn’t take long before the building came down!

Gallery Image
Removal of the Hands on Learning Portable
Gallery Image
Gallery Image
Science Room
Gallery Image
Gallery Image
Gallery Image
Removal of the Hands on Learning Portable
Science Room
Gallery Image

The demolition crew has also been busy inside Building B which is the Art, Science, and Staffroom areas. On Thursday, we saw some of the roof removed as part of the process.

Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image

 

Week 6

Monday 25th August the walk way attaching the builds was removed. Along with all cladding that was on the walls.

Gallery Image

The Hands on Learning building has be completly cleared away and the roof of the science room has been removed

Gallery Image
Gallery Image

 

The crushing of Building B, Art, Science, and Staffroom areas

 

Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Before
Gallery Image
Mid Way
Gallery Image
After
Before
Mid Way
After
Gallery Image