Building and Grounds News

Capital Works update

There is a lot of work being completed at the moment in the Kiss N Go area and staff car parking.  In two weeks this area will have been completely overhauled.

 

The area in front of the gallery and leading to the oval is also undergoing a complete transformation.  New walls constructed and concreting will be poured over the holiday period.

 

It is an exciting period for CSPS with the work going on. Thanks to the community for keeping an eye on our school in this time.

 

Current Progress (completed last fortnight)  

  • misc framing, truss support, blocking out 
  • ex. retaining wall removal 
  • new retaining wall @ 50% 
  • bored piers complete - stormwater complete

Anticipated works for Next Fortnight  

  • retaining wall ongoing 
  • misc framing ongoing 
  • truss site measure 
  • car park kerb & channel commencement