Building and Improvement Projects

Building Works

 

As most of you would be aware, our school will be undertaking some building and refurbishment works throughout this term:

 

1. Re-surfacing of the Outdoor Basketball and Netball Court area.

2. Removal of School portables from the West end of the Campus; and 

3. Refurbishing the Car Park area at the East end of the Campus.

 

As a result of these works, we need to put some general rules and guidelines in place to ensure everyone's safety and clearance of these areas. 

 

There is going to be areas of the school that will be fenced off with temporary fencing to stop unauthorised people accessing these areas throughout the period of time these works are completed. We ask that all students, parents and staff stay well away from these areas for your own safety, and that you have a greater awareness of large machinery and trucks in these areas throughout this Term.

 

In addition to this, Year 12 students may need to access the main East Wing building from the front entrance rather than through the Girls Breezeway as they normally do, due to the works. We encourage you all to act safely and cautiously when accessing the East Wing from the Year 12 room.

 

All students are also to be aware not to bring mud and other remnants from these works inside, as grassed areas may become quite 'torn up' with the recent rain and trucks and machinery accessing these areas.

 

Students riding bikes to and from school may ride along the footpath to and from the direction of Goodwin Village, but if they are entering from the East end gate of the Campus (from Camp Street), please get off your bike and walk your bike to the bike shelter as traffic in this area will be busy. 

 

Cars and students riding are also asked to not use the West end entrance (off Stawell Road) at the back of the school please until the end of the week (Friday 1st August). 

 

When the East end Car Park works are being completed, we also ask that cars use the West end Car Park (off Camp Street) please to access the school.

 

Update

 

The removal of the portables is nearly completed. Below are some photos of the removal.

 

 

The removal of netball court area has been completed and now the levelling of the area has begun.