Capital Works - Kildare Campus

It's all action stations at our Kildare Campus! Here is an update of the latest works!
Admin Building
- Framing 100% complete and skylight in place.
- Roofing to be installed next.
- Services rough in commenced on plumbing & electrical. Mechanical to commence next week.
- Window frames to be installed next week.
Learning Building
- 50% Steel erected with balance fabricated and delivered within next two weeks.
- Wall framing to commence, trusses due next week.
Other Works
- Columns to front gate installed, brickwork to commence next week.
- Once brickwork completed on gate, then to commence Admin Building.
- Slab to Fire Tank installed.
- Steel arches arrived on-site.
- Bike shelter footings completed, pour to be completed on Monday.
- Main switchboard and services connection to sub-station commenced.
Cheryle Ryan
Business Manager