Capital Works - Kildare Campus

It's all action stations at our Kildare Campus! Here is an update of the latest works!

 

 

Admin Building

  • Framing 100% complete and skylight in place.
  • Roofing to be installed next.
  • Services rough in commenced on plumbing & electrical. Mechanical to commence next week.
  • Window frames to be installed next week.

 

Learning Building

  • 50% Steel erected with balance fabricated and delivered within next two weeks.
  • Wall framing to commence, trusses due next week.

 

Other Works

  • Columns to front gate installed, brickwork to commence next week.
  • Once brickwork completed on gate, then to commence Admin Building.
  • Slab to Fire Tank installed.
  • Steel arches arrived on-site.
  • Bike shelter footings completed, pour to be completed on Monday.
  • Main switchboard and services connection to sub-station commenced.

 

Cheryle Ryan

Business Manager