Capital Works - Kildare Campus

While the flood events over the past two weeks have had significant impacts on our region, we are lucky that work continues to progress at our Kildare Campus including:

  • Learning Building wall framing - roof and walls 95% complete
  • Learning Building window framing - 85% complete
  • Learning Building brickwork - 10% complete
  • Admin Building door hardware - 25% complete
  • Admin Building metal wall cladding - 70% complete
  • Admin Building plaster board lining - 25% complete
  • Landscaping paths base material - complete
  • Larger plants and trees delivered to site for planting - 80% complete

 

Upcoming Works (weather permitting):

  • Learning Building roof carpentry to be completed
  • Learning Building plumbing and electrical rough in to be completed
  • Learning Building roof to be completed in 2 weeks
  • Admin Building - plastering to continue 
  • Admin Building - timber wall cladding to continue
  • Admin Building - metal wall cladding to commence

 

Cheryle Ryan

Business Manager