New Campus Update
Early-stage site preparation activities are in progress at our new campus site on Molesworth Street led by builders, Hansen Yuncken (HY).
A comprehensive traffic management plan has been developed by HY for the construction site works. Throughout the project, the traffic management plan will aim to ensure construction activities are undertaken safely and efficiently while providing for the safety of all road users, pedestrians and construction personnel. The traffic management plan includes strategies to minimise impacts to the environment along with disruption to pedestrian activities and local vehicle traffic. If there is any need to vary our walking routes to school during the construction, we will keep you updated.
Upcoming works scheduled include:
- Q3: Establishing hoarding, site sheds and ground leveling
- Q3: Commence piling and excavation
- Q4: Pour ground slabs and commence suspended structure.
Should you have any specific building-related issues or queries during the construction of the project, please contact Hansen Yuncken’s site manager Peter Free. Email: Melbourne@hansenyuncken.com.au Telephone: 9831 6500
Keep up-to-date about our new campus during its construction
Visit the Victorian School Building Authority website
www.schoolbuildings.vic.gov.au/schools/Pages/NthMelbournePSNewCampus.aspx
Subscribe to our project update newsletter on the North Melbourne Primary School web page
Follow project news on LinkedIn and Facebook
Email vsba@education.vic.gov.au
Telephone 1800 896 950
School zone information will be released early in 2022 on findmyschool.vic.gov.au