Capital Works - Kildare Campus

Despite heavy rain over the past few weeks we have still seen some significant progress at our Kildare Campus including:
- Learning Building wall framing now 90% complete.
- Administration roofing 95% complete.
- Learning Building structural steel is 95% complete.
- Administration pressed metal door frames have been installed.
- Brickwork to entry gate complete.
Hopefully some sunshine over the holidays will allow the following works to be completed over the coming weeks:
- Learning Building trusses to be completed.
- Learning Building plumbing and electrical rough in.
- Balance of Learning Building steel erection.
- Admin Skylight to be installed.
- Admin masonry to commence.
- Admin external cladding.
- Learning Building Roof with safety wire to commence.
Cheryle Ryan
Business Manager