Capital Works - Kildare Campus

Despite heavy rain over the past few weeks we have still seen some significant progress at our Kildare Campus including:

  • Learning Building wall framing now 90% complete.
  • Administration roofing 95% complete.
  • Learning Building structural steel is 95% complete.
  • Administration pressed metal door frames have been installed.
  • Brickwork to entry gate complete.

 

Hopefully some sunshine over the holidays will allow the following works to be completed over the coming weeks:

  • Learning Building trusses to be completed.
  • Learning Building plumbing and electrical rough in.
  • Balance of Learning Building steel erection.
  • Admin Skylight to be installed.
  • Admin masonry to commence.
  • Admin external cladding.
  • Learning Building Roof with safety wire to commence.

Cheryle Ryan

Business Manager