Art/Technology Building
The Art/Technology building is scheduled to be completed and handed over to the school on the 27th of August which is not far away now !
Interior works are continuing with floor vinyl now being laid; equipment being installed; painting being completed and fitoff of electrical systems, dust extraction and air compression systems.
Externally the roof works are complete (with all the moss finally off the apex windows - how bright it now is inside !); landscaping is underway with new feature trees and pavement areas completed and most painting is finished - providing a new lease of life to the look of the building.
We are looking forward to beginning the move in process and we anticipate commencing all technology and visual art classes in the building for the start of term 4.