Capital Works Update
STAGE 3 CONSTRUCTION UPDATE
Capital Works Update
STAGE 3 CONSTRUCTION UPDATE
Over the last few weeks, in between complete shutdowns, Nicholson Construction have continued on-site with a team of 5 workers (25% capacity), to comply with current restrictions.
This is putting our completion plans for the Sheehan Wing Ground Floor behind by at least 4 weeks and the Sports Arena at a complete standstill.
Our hope is that in coming weeks more workers will be allowed on-site, and progress can speed up.
Notwithstanding all this – below are a few pics to show some plastering works that have been occurring. Please note the colours showing are the raw plaster – not the final paint finish!