Capital Works Update

STAGE 3 CONSTRUCTION UPDATE

Over the last few weeks, in between complete shutdowns, Nicholson Construction have continued on-site with a team of 5 workers (25% capacity), to comply with current restrictions.

 

This is putting our completion plans for the Sheehan Wing Ground Floor behind by at least 4 weeks and the Sports Arena at a complete standstill.

 

Our hope is that in coming weeks more workers will be allowed on-site, and progress can speed up.

 

Notwithstanding all this – below are a few pics to show some plastering works that have been occurring. Please note the colours showing are the raw plaster – not the final paint finish!

New library ceiling, with “holey” acoustic plaster board inserts to absorb sound.
New library ceiling, with “holey” acoustic plaster board inserts to absorb sound.
New library staff office windows, located to the right of the glass sliding entrance doors.
New library staff office windows, located to the right of the glass sliding entrance doors.
The new entrance to the Student Wellbeing Hub.
The new entrance to the Student Wellbeing Hub.

 

 

 

 

 

 

 

 

 

 

A dedicated teaching space has been created at the west end of the library.
A dedicated teaching space has been created at the west end of the library.