Capital Works - Kildare Campus

The building works at Kildare Campus have obviously been impacted by the recent inclement weather, but progress still remains positive and we are hopeful some sunshine and dry weather over the summer months will enable us to reclaim time!

 

Progress over the past four weeks:

  • Learning Building wall framing - roof and walls 90% complete
  • Learning Building window framing - 50% complete
  • Admin Building windows - 100% complete
  • Admin Building brickwork - 100% complete
  • Admin Building door hardware - 25% complete
  • Admin Building metal wall cladding - 50% complete
  • Rammed earth walls to pedestrian and main entrance commenced
  • Paths, landscaping and planting commenced

 

Upcoming works (weather permitting):

  • Learning Building roof carpentry to be completed
  • Learning Building plumbing and electrical rough in to be completed
  • Learning Building roof to be completed in 3 weeks
  • Admin Building - plastering to commence
  • Admin Building - timber wall cladding to commence
  • Admin Building - metal wall cladding to commence
  • Landscaping footpaths around Administration Building to be completed

 

Cheryle Ryan

Business Manager