Community Announcements
Coles Development
Over the past week the site had seen significant progress, see below milestones.
- Completion of Upper Ground pour three columns.
- Completion of Upper Ground pour three suspended slabs.
- Completion of level 1 (pour one) formwork.
- Commenced all stripping to lower ground 1 slab.
- Installation of 20 precast panels to the Northern Boundary.
Over the coming week I anticipate the below works to be commenced and completed.
- Commencement of the Level 1 (pour two) formwork.
- Installation of precast panels to the northern elevation Wednesday 22/11/2023
- Tower Boom top-up on Thursday 23/11/2023.
- Pouring of the UG Pour one raised section columns and slab on 21/11/2023.