Kildare Campus Stage 2 update from St. Joseph's College

If you have taken a drive out to St. Joseph's College's new Kildare Campus lately you will have noticed the huge amount of progress that has taken place on both the learning and specialist buildings! 

 

Stage 2 works are currently all running to program, in fact they are actually slightly ahead!

Hopefully the weather will be kind over the coming months and they can stay on track for the remainder of the year.

 

Progress to Date

  • Specialist building steel completed.
  • Learning building steel completed
  • Stormwater completed.
  • Sewer connection completed.
  • Roofing to specialist building 50% complete.
  • Specialist building wall framing 60% complete.
  • Specialist building rough in services 10% complete.

What's Next

  • Roofing and framing on learning building to commence.
  • Specialist services rough in to continue.
  • Installation of windows to commence.
  • Bricklayer to commence.
  • Specialist building mechanical work and duct work to commence.
  • Additional mulch to be installed around the outdoor gym.
  • COLA structure over outdoor courts to commence.

 