Please find attached the resident letter notification which will be letter dropped to the affected residents.
As informed in the letter we have finalised a contractor and it is proposed to commence the works in three stages.
Stage 1 which includes the works in Furneaux Gr between Mcwhae Av and Loch Av is to commence from Monday 18 March 2024.
Stage 3 will involve works in the intersection of Carrington Gr, Greenmeadows Ln and Furneaux Gr.
Stage 3 is expected to commence from 20 May subject to weather and other restrictions.
There will be some parking restrictions for 15m-20m near the road closure inside Carrington Gr to assist U-turn.
There will be no further parking restrictions in Carrington Gr, however Council traffic engineers will monitor the traffic once the work commences to asses any further parking restrictions if required.
SCHOLASTIC BOOK CLUB
This term, we have had a competition to design a new logo for Scholastic Book Club.
The overall winner of the competition was Harriet L from 34B.
Lottie K from 34A also received an Honourable Mention award.
Congratulations Harriet and Lottie!
Thank you to everyone who submitted a design, the judges were impressed by all the creative logos.
All the designs will be on display in the library next term.