While the school was quiet over the holidays, our building site certainly wasn't.
Work on the development has continued at a steady pace, and we're pleased to share the progress made:
- Bulk and detailed excavation works have continued across the site
- The site crane has been installed and commissioned
- Piling works have progressed
- Trenching in the Tivoli courtyard was completed, with the lawn now replaced
- The accessible bathroom in the Music Centre has been rebuilt
We're excited to see the project taking shape and look forward to keeping you updated as work continues through the term. Thank you for your patience while these important works are underway.
Dr Tamara Lang
Deputy Principal - Strategy, Development and Operations