Kildare Campus Update

If you have taken a drive out to Kildare Campus lately you will have noticed the huge amount of progress that has taken place on both the learning and specialist buildings! 

 

Stage 2 works are currently all running to program, in fact they are actually slightly ahead!

Hopefully the weather will be kind to us over the coming months and we can stay on track for the remainder of the year.

Progress to Date

  • Specialist building steel completed
  • Learning building steel completed
  • Stormwater completed
  • Sewer connection completed
  • Roofing to specialist building 50% complete
  • Specialist building wall framing 60% complete
  • Specialist building rough in services 10% complete

What's Next

  • Roofing and framing on learning building to commence
  • Specialist services rough in to continue
  • Installation of windows to commence
  • Bricklayer to commence
  • Specialist building mechanical work and duct work to commence
  • Additional mulch to be installed around the outdoor gym
  • COLA structure over outdoor courts to commence

 

 

New Outdoor Seating

 

As Kildare Campus continues to grow, we have ordered more outdoor seating to accomodate for the extra children next year and to provide greater options for students to gather during recess and lunch, and also for outdoor classes.

 

These include:

  • 6 outdoor pods 
  • 2 outdoor recycled plastic tables in school colours 

 

 

 

Lunchtime Activities