Coles Development
Over the past week the site had seen significant progress, see below milestones:
- Completion of UG Pour Four columns.
- Completion of UG Pour One raised section
- Commencement of the Level One pour Two formwork
- Commenced all stripping to Lower Ground One slab
- Installation of 20 precast panels to the Northern Boundary
Over the coming week we anticipate the below works to have commenced and be completed:
- Commencement of the Level 1 (Pour 2) formwork
- Installation of Precast Panels to the Northern Elevation on Saturday the 02/12/2023
- Tower boom top-up on Tuesday 28/11/2023
- North-West corner Scaffolding top up
- Pouring concrete for Upper Ground (Pour 4) on Thursday 30/11/2023