Over the past week the site had seen significant progress, see below milestones:

  • Completion of UG Pour Four columns. 
  • Completion of UG Pour One raised section  
  • Commencement of the Level One pour Two formwork
  • Commenced all stripping to Lower Ground One slab
  • Installation of 20 precast panels to the Northern Boundary

Over the coming week we anticipate the below works to have commenced and be completed:

  • Commencement of the Level 1 (Pour 2) formwork
  • Installation of Precast Panels to the Northern Elevation on Saturday the 02/12/2023
  • Tower boom top-up on Tuesday 28/11/2023 
  • North-West corner Scaffolding top up