Community Announcements
Coles Development Update
Over the past week the team have made significant progress with the site, the completed works achieved are:
- Completion of Upper Ground Pour 1 Slab.
- Commencement of the Suspended deck on Upper Ground Pour 3.
- Commencement of the Suspended deck on Level 1.
- Completion of all Lifts & Fire Stair Cores.
Works that are targeted for the remainder of the week are:
- Concrete Pour to Lower Ground 1 Pour 4 on Tuesday 31/10/2023.
- Concrete Pour to LG1-UG Pour 2 on the Saturday 4/11/2023.
- Continuation with Formwork to the Upper Ground Slab.