Coles Development Update 

Over the past week the team have made significant progress with the site, the completed works achieved are:

  • Completion of Upper Ground Pour 1 Slab. 
  • Commencement of the Suspended deck on Upper Ground Pour 3.
  • Commencement of the Suspended deck on Level 1. 
  • Completion of all Lifts & Fire Stair Cores.

 

Works that are targeted for the remainder of the week are: 

  • Concrete Pour to Lower Ground 1 Pour 4 on Tuesday 31/10/2023.
  • Concrete Pour to LG1-UG Pour 2 on the Saturday 4/11/2023.
  • Continuation with Formwork to the Upper Ground Slab.