Kildare Campus Update

The weather has been kind to us, enabling Stage 2 works to be completed at an exceptional rate at our Kildare Campus!

Current Progress:

  • Roofing to Specialist Building – 90% complete, flashing/trims to be finished
  • Wall framing to Specialist Building – 100% complete with inspection pending
  • Specialise rough in services – 70% complete, inspection within 2 weeks
  • Roofing to Learning Building – 70% complete, wiring complete, handrail/roofing sheets this week
  • Wall Framing to Learning Building – 90% complete
  • Solar Panel installation on Specialist Building – 50% complete
  • Window/door frames – 70% complete with glazing by end of week.  Doors to follow
  • Slider door tracks to both buildings complete
  • Soffits/fascia started – 75% complete

Anticipated Program for the Next Fortnight:

  • Specialise services rough in – ongoing
  • Bricklayer to commence
  • Plaster to start
  • Learning Building – solar panel installation
  • Some joinery to be installed before Christmas
  • Specialist building to be at lock up stage before Christmas
  • Extension to pathway next to external lockers Learning Building
  • Finishing touches to cement around well

 

Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image
Gallery Image