Kildare Campus Update

The weather has been kind to us, enabling Stage 2 works to be completed at an exceptional rate at our Kildare Campus!

Current Progress:

  • Roofing to Specialist Building – 90% complete, flashing/trims to be finished
  • Wall framing to Specialist Building – 100% complete with inspection pending
  • Specialise rough in services – 70% complete, inspection within 2 weeks
  • Roofing to Learning Building – 70% complete, wiring complete, handrail/roofing sheets this week
  • Wall Framing to Learning Building – 90% complete
  • Solar Panel installation on Specialist Building – 50% complete
  • Window/door frames – 70% complete with glazing by end of week.  Doors to follow
  • Slider door tracks to both buildings complete
  • Soffits/fascia started – 75% complete

Anticipated Program for the Next Fortnight:

  • Specialise services rough in – ongoing
  • Bricklayer to commence
  • Plaster to start
  • Learning Building – solar panel installation
  • Some joinery to be installed before Christmas
  • Specialist building to be at lock up stage before Christmas
  • Extension to pathway next to external lockers Learning Building
  • Finishing touches to cement around well