Building and Grounds News

Capital Works update
Current Progress (completed last fortnight)
- Trusses completed -
- Timber roof battens - 1/3 complete
- Window frames - 80% installed - Pearcedale road works complete
- Miscellaneous framing underway
Anticipated works for Next Fortnight
- Miscellaneous roof and wall framing to be completed
- Roof battening to be completed
- Roof sheeting measure to commence
- External wall starting to commence
- Eastern civil works to commence
- Plumbing, electrical and mechanical rough-in to commence
- Roof sheet measure-up (installation on Sat 20th)
- Final framing inspection from the Building Surveyor
- Works associated with changing site access to near the Multipurpose building
LIBRARY UPDATE
As part of the Capital Works our HUB - Library and Google Studio will also be undergoing a transformation. Many thanks to the team of volunteers who have packed up the library resources in order for it to be emptied. This was a mammoth task! Thanks for your help.