Building and Grounds News

Capital Works update

Current Progress (completed last fortnight)

  • Trusses completed -
  • Timber roof battens - 1/3 complete 
  • Window frames - 80% installed - Pearcedale road works complete
  • Miscellaneous framing underway

Anticipated works for Next Fortnight 

  • Miscellaneous roof and wall framing to be completed 
  • Roof battening to be completed 
  • Roof sheeting measure to commence 
  • External wall starting to commence 
  • Eastern civil works to commence 
  • Plumbing, electrical and mechanical rough-in to commence 
  • Roof sheet measure-up (installation on Sat 20th) 
  • Final framing inspection from the Building Surveyor 
  • Works associated with changing site access to near the Multipurpose building 