Banner Photo

CAPITAL WORKS UPDATE

Progress of the stage 3 works includes extensive demolition, ground works and underpinning. Some internal work has commenced particularly in the Performing Arts Centre.

Gallery Image
Modification works to form new openings in existing walls
Gallery Image
Dance & Band rooms
Gallery Image
Timber ramp framed & floor sheeted Collaborative space
Gallery Image
Under pining works of external footing
Gallery Image
Under pining works of external footing
Gallery Image
Planter box strip footing (Inc. starter bars) pour on South side
Gallery Image
Installation of new storm-water & connection into existing infrastructure
Gallery Image
Gallery Image
Demolition & removal of Bldg 4 suspended concrete floor slab
Gallery Image
Status of ceilings & walls Blg 4 Collaborative space & Dance Room
Gallery Image
Footing excavation commenced & ongoing Building 1 (Admin)
Modification works to form new openings in existing walls
Dance & Band rooms
Timber ramp framed & floor sheeted Collaborative space
Under pining works of external footing
Under pining works of external footing
Planter box strip footing (Inc. starter bars) pour on South side
Installation of new storm-water & connection into existing infrastructure
Demolition & removal of Bldg 4 suspended concrete floor slab
Status of ceilings & walls Blg 4 Collaborative space & Dance Room
Footing excavation commenced & ongoing Building 1 (Admin)