Kildare Campus Update

Our Specialist Building is really starting to take shape and students and staff alike are enjoying watching the space transform every day right before their very eyes!  

 

 

 

Progress Update:

  • Concrete complete on both buildings
  • Specialist Building steel frame - 70% complete (to be completed mid next week)
  • External stormwater - 90% complete (junctions to downpipes still to be done)
  • Plumbers have been onsite, working on the west side of the Specialist Building undertaking sewer connections

 

Upcoming Progress:

  • Specialist Building steel frame to be completed
  • Learning Building steel frame to start early next week
  • Sewer for in-ground services to be completed
  • Roof works to commence on Specialist Building
  • Steel inspection to be undertaken early next week
  • Wall framing to Specialist Building to commence next week

 

 

Cheryle Ryan

Business Manager