Kildare Campus Update
![](https://media.naavi.com/macaroni/im-8a99d5e4-07de-4920-b018-d2599333077d.jpg?deg=auto&w=2400&h=2400)
Our Specialist Building is really starting to take shape and students and staff alike are enjoying watching the space transform every day right before their very eyes!
Progress Update:
- Concrete complete on both buildings
- Specialist Building steel frame - 70% complete (to be completed mid next week)
- External stormwater - 90% complete (junctions to downpipes still to be done)
- Plumbers have been onsite, working on the west side of the Specialist Building undertaking sewer connections
Upcoming Progress:
- Specialist Building steel frame to be completed
- Learning Building steel frame to start early next week
- Sewer for in-ground services to be completed
- Roof works to commence on Specialist Building
- Steel inspection to be undertaken early next week
- Wall framing to Specialist Building to commence next week
Cheryle Ryan
Business Manager