Over the past week the site had seen significant progress, see below milestones.
- Commencement of the Level One Pour Two formwork.
- Installation of Precast Panels to the Northwest Elevation on Wednesday the 06/12/2023.
- Tower Boom top-up on Thursday the 07/12/2023.
- Pouring concrete for UG to Level One Verticals on Thursday the 07/12/2023.
- Commencement of striping on LG One.
Over the coming week I anticipate the below works to be commenced and completed.
- Commencement of the Level One Pour Three formwork.
- Pouring concrete for UP to Level One Verticals on Tuesday the 11/12/2023.
- Commencement of striping on LG One.