Facilities News 

Dr Denise Clarke              Frances Hansen

Capital Works Manager     Facilities Manager

Facilities Works 

Works around the school:

  • Birds Nest Swing rubber soft fall will be installed next week. 
  • Items from the Playground audit are being remediated.
  • Contractors have been booked for upgrade of Secondary toilets during Term 3 holidays.
  • Contractors have been booked to replace roof, gutters and eaves of portables encompassing HLK and Room 20 during Term 3 holidays.

Planning is commencing for major projects to be considered for funding in 2024. 

Capital Works 

The new Yaluk Building is moving along well. All the steel infrastructure has been installed and currently roofing insulation and cladding is being added to the building. 

 

Cladding & roof cladding being installed.
Cladding & roof cladding being installed.

 

Canteen side of building
Canteen side of building

 

Western end of building
Western end of building