This is our final Kildare Campus capital works update for 2022. We are delighted with the progress over the past 6 weeks, and as you can see from the photographs below, the campus is really taking shape now. Amazing the difference some sunny weather can make! Let's pray that it continues.

 

 

Progress to date (as at 1 December):

 

  • Learning building Glazing 90% complete
  • Learning building Roof 90% complete
  • Learning building brickwork 90% complete
  • Administration building plaster board lining 95% complete
  • Water Tanks 70% complete
  • Bike Shelter 100% complete

 

Works scheduled over the next two weeks (weather permitting):

  • Learning building rough in to be 100% complete
  • Learning building plaster to commence
  • Learning building soffits to commence
  • Administration building skylight to be installed
  • Administration building flooring to commence
  • Administration building painting to commence
  • External paving

Our next site meeting is scheduled for Thursday 15 December 2022.

 