Capital Works - Kildare Campus
![](https://media.naavi.com/macaroni/im-107f826a-0acf-4d3a-b94e-33c142ccab40.png?deg=auto&w=2400&h=2400)
The administration and learning buildings are really starting to take shape at our new Kildare Campus at Mt Terrick Rd!
Since our last newsletter:
- 95% of the trusses for the Admin Building are now complete.
- Water has been connected.
- Steel is complete from Grids A-F on the Learning Building.
Next two weeks:
- Carpentry to be completed on Admin Building.
- Balance of steel to be delivered for Learning Building.
- Masonry to commence to Admin Building.
- Aluminium window frames to be installed.
- Roofing to commence on Admin Building.
- Services rough in to Admin Building.
Cheryle Ryan
Business Manager