Capital Works - Kildare Campus

Improved weather conditions over the last couple of weeks have resulted in some exciting progress at our Kildare Campus. 

 

Progress to date:

  • Learning building wall framing - 100% complete roof and walls
  • Learning building window framing - 100% complete
  • Learning building brickwork - 45% complete
  • Administration building plaster board lining - 50% complete
  • Administration building metal wall cladding - 90% complete

 

Works to be completed over the next two weeks are as follows (weather permitting):

  • Learning building plumbing and electrical rough in to be completed
  • Learning building roof to be completed
  • Learning building external glazing to be completed
  • Administration building plastering to continue
  • Administration building timber wall cladding to continue
  • Administration building metal facias, soffits and barges to commence
  • External paving to commence

 

Cheryle Ryan

Business Manager